Draw sequencing
If two lenders fund later than expected, where does the working-capital burden land?
An illustrative case scenario
Explore a hypothetical development portfolio to see why an on-budget project can still create a near-term cash squeeze. This is not an actual engagement or verified client outcome.
The situation
Imagine a founder-led developer overseeing five active projects totaling $47 million. Each project manager tracks budgets and committed costs. A controller closes the books, while draw submissions live in separate spreadsheets.
In this fictional exercise, leadership looks at the next 90 days across all five projects instead of one project at a time.
Illustrative calculations only, not a discovered or avoided loss.
The questions that matter
If two lenders fund later than expected, where does the working-capital burden land?
Are pending change orders already reflected in the cash and cost-to-complete views?
Which funding choices require action now rather than at the next reporting cycle?
How to use this scenario
The $2 million gap is deliberately hypothetical. The point is that costs, draws and equity can be accurate in isolation yet misaligned across a portfolio. A rolling cash forecast reveals those dependencies before a critical funding decision.